All stations nominal —

Rotor line

EESM wound rotorM010 → M060 · 11 stations—
in flight—
—rotors / hour
line takt 30 / h · set by M040 at 120 s—

Waiting for the first shift readout…

—
OEE · today
A—P—Q—
—
First-pass yield
—
—
Shift output · target
—
—
Lineside stock @A020
—

The line

shaft → laminations → winding → slip rings → varnish → HV test → balancing → marking → final test running loading blocked · downstream full fault break idle
Queue = pieces waiting on the inbound conveyor · capacity 3 — a full queue blocks the station upstream. Review the 11 product stages Open the shopfloor view

Shift pace

rotors per hour · last 8 h—
Built this shift—
Projected at shift end—
Current pace—
Crew on line—

Stops

last 24 h · by cause · minutes down—
Loading…

Scrap

last 24 h · by reason—
Loading…

Stations

live state · today's counts · piece in the machine
StationOperationStateCycleQueueParts todayFPYScrap · reworkIn machineLast stop